Sunday, June 1st thru Saturday, June 7th:
1. 30 Eastbound Left Lane from FM 548 to FM 2642. Overnight. 9P-5A. Bridge activities at FM 35 and Sabine Creek.
2. 30 Westbound Left Lane from FM 2642 to FM 548. Overnight. 9P-5A. Bridge activities at FM 35 and Sabine Creek.
3. 30 Eastbound Left Lane at FM 3549. Overnight. 9P-5A. Embankment, removals and bridge activities at FM 3549.
4. John King Blvd. Full closure. 30 Eastbound frontage road to 30 Westbound frontage road. Overnight. 9P-5A. Demo bridge deck.
5. 30 Westbound Left Lane from Fate Main PL to Ben Payne. Overnight. 9P-5A. Embankment/Removals.
Monday, June 2nd thru Saturday, June 7th:
1. John King East to West U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
2. John King West to East U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
3. FM 548 NB/SB. Flagging Operation. Daytime. 9A-3P. Drainage work and bridge activities at Pond Branch.
4. 30 Eastbound Frontage Road Left Lane from SH 205 to T L Townsend Dr. Daytime. 9A-3P. Drainage work activities.
5. 30 Westbound Frontage Road Left Lane from T L Townsend Dr. to SH 205. Daytime. 9A-3P. Embankment, removals, and installation of LPCB.
6. FM 3549. East to West U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
7. FM 3549. West to East U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
Contractor crews will work with EMS, fire, and police to allow access through the closure should emergencies occur.