Sunday, July 27th thru Saturday, August 2nd:
1. 30 Eastbound Left Lane from FM 548 to FM 2642. Overnight. 9P-5A. Bridge activities at FM 35 and Sabine Creek.
2. 30 Westbound Left Lane from FM 2642 to FM 548. Overnight. 9P-5A. Bridge activities at FM 35 and Sabine Creek.
3. 30 Westbound Left Lane from Fate Main PL to FM 3549. Overnight. 9P-5A. Removals and Placing Hot Mix.
4. 30 Eastbound Left Lane at FM 3549. Overnight. 9P-5A. Embankment and Removals.
5. 30 Westbound Frontage Road Left Lane from Townsend Dr to SH 205. Overnight. 9P-5A. Removals and Place Hot Mix.
Monday, July 28th thru Saturday, August 2nd:
1. John King East to West U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
2. John King West to East U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
3. FM 548 NB/SB. Flagging Operation. Daytime. 9A-3P. Drainage work and bridge activities at Pond Branch.
4. 30 Eastbound Frontage Road Left Lane from SH 205 to Townsend Dr. Daytime. 9A-3P. Embankment and removals.
5. 30 Westbound Frontage Road Left Lane from Townsend Dr to SH 205. Daytime. 9A-3P. Install Low Profile Concrete Barrier.
6. FM 3549. East to West U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
7. FM 3549. West to East U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
Contractor crews will coordinate with EMS, fire, and police to permit access through the closure if emergencies arise.