Tuesday, September 2nd thru Saturday, September 6th:
1. John King East to West U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
2. John King West to East U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
3. I-30 Eastbound Left Lane from FM 548 to FM 2642. Overnight. 9P-5A. Bridge and earthwork activities at Sabine Creek and FM 35.
4. I-30 Westbound Left Lane from FM 2642 to FM 548. Overnight. 9P-5A. Bridge and earthwork activities at Sabine Creek and FM 35.
5. FM 548 NB/SB. Flagging Operation. Daytime. 9A-3P. Embankment, Removals, and bridge activities at Pond Branch.
6. FM 3549. East to West U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
7. FM 3549. West to East U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
8. I-30 Westbound Left Lane from Fate Main PL to FM 3549. Overnight. 9P-5A. Placing Hot Mix & Pavement activities.
9. I-30 Eastbound Left Lane at FM 3549. Overnight. 9P-5A. Embankment and removals.
10. I-30 Westbound Frontage Road Left Lane from FM 548 to Erby Campbell. Daytime. 9A-3P. Embankment and removals.
Please be advised: There will be no work August 29th through September 1st. Work will resume on Tuesday, September 2nd.
Contractor crews will work closely with EMS, fire, and police to facilitate access through the closures in the event of emergencies.