Saturday, October 11th thru Monday, October 13th:
1. I-30 Westbound Frontage Road. Full Closure of Townsend. Continuous. 1P-7P. Install Drainage Pipe Crossing Townsend.
Sunday, October 12th thru Saturday, October 18th:
1. I-30 Eastbound Left Lane from FM 548 to FM 2642. Overnight. 9P-5A. Bridge and earthwork activities at Sabine Creek and FM 35.
2. I-30 Westbound Left Lane from FM 2642 to FM 548. Overnight. 9P-5A. Bridge and earthwork activities at Sabine Creek and FM 35.
Monday, October 13th thru Saturday, October 18th:
1. FM 548 NB/SB. Flagging Operation. Daytime. 9A-3P. Embankment, Removals, and bridge activities at Pond Branch.
2. FM 3549. East to West U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
3. I-30 Eastbound Frontage Road from FM 551 to Erby Campbell. Flagging Operation. Daytime. 9A-3P. Unload Drainage Boxes.
4. I-30 Eastbound Frontage Road Left Lane from FM 3549 to Rochell Rd. Overnight. 9P-5A. Install Temp Pavement Markings.
5. I-30 Eastbound Frontage Road Left Lane from Industrial Rd to E Fate Main PL. Overnight. 9P-5A. Install Temp Pavement Markings.
6. I-30 Westbound Frontage Road from College Ave to FM 548. Flagging Operation. Overnight. 9P-5A. Install Temp Pavement Markings.
Tuesday, October 14th thru Friday, October 17th:
1. I-30 Eastbound Frontage Road. Full Closure of Townsend. Continuous. 8A-7P. Install Drainage Pipe Crossing Townsend.
Monday, October 13th thru Monday, October 20th (Continuous):
1. John King E/W U-turn closure. Continuous. 9A-5A. Bridge Activities at John King.
2. John King W/E U-turn closure. Continuous. 9A-5A. Bridge Activities at John King.
Friday, October 17th thru Monday, October 20th (Continuous):
1. John King Blvd from the I-30 Eastbound Frontage Road to the I-30 Westbound Frontage Road. Continuous Full Closure. 9P-5A. Bridge Activities at John King.
Contractor crews will coordinate with emergency medical services (EMS), fire departments, and police to ensure that access is maintained through the closure in the event of any emergencies.
Also, from Rockwall County Road & Bridge:
We are scheduled to complete the work on McDonald Road by Tuesday. Please be aware that there may be single lane closures during this period.
Once the work on McDonald Road is finished, our focus will shift to Camp Creek Road.
From the City of Heath
The Texas Department of Transportation (TxDOT) is working on South FM 740 this week, from Monday to Friday, between 9 p.m. and 5 a.m. Crews will be replacing the blacktop from the intersection of FM 740 and Laurence Drive to the county line. During these hours, one lane in each direction will be closed. Flag crews will be on site to direct traffic.