Sunday, November 2nd thru Saturday, November 8th:
1. John King East to West U-turn closure. Overnight. 9P-5A. Bridge activities at John King.
2. John King West to East U-turn closure. Overnight. 9P-5A. Bridge activities at John King
3. I-30 Eastbound Left Lane from FM 548 to FM 2642. Overnight. 9P-5A. Bridge and earthwork activities at Sabine Creek and FM 35.
4. John King Blvd. I-30 Eastbound Frontage Road to I-30 Westbound Frontage Road. Full Closure. Overnight. 9P-5A. Bridge Activities at John King.
5. I-30 Eastbound Left Lane at FM 3549. Overnight. 9P-5A. Bridge Activities and Placing Cement Treated Base.
Monday, November 3rd thru Saturday, November 8th:
1. FM 548 Northbound/Southbound. Flagging Operation. Daytime. 9A-3P. Embankment, Removals, and bridge activities at Pond Branch.
2. FM 3549. East to West U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
3. FM 3549. West to East U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
4. I-30 Westbound Frontage Road. Flagging Operation. From FM 35 to Erby Campbell. Daytime. 9A-3P. Install Low Profile Concrete Barrier.
5. I-30 Eastbound Frontage Road from FM 551 to Erby Campbell. Flagging Operation. Daytime. 9A-3P. Unload Drainage Boxes and Install Low Profile Concrete Barrier.
Contractor crews will coordinate with EMS, fire, and police to facilitate access during the closure if emergencies arise.