Planned lane closures on IH 30 through Rockwall County for the upcoming week:
Monday, May 12th thru Saturday, May 17th:
1. John King East to West U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
2. John King West to East U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
3. 30 Eastbound Left Lane closed from FM 548 to FM 2642. Overnight. 9P-5A. Bridge activities at FM 35 and Sabine Creek.
4. 30 Westbound Left Lane closed from FM 2642 to FM 548. Overnight. 9P-5A. Bridge activities at FM 35 and Sabine Creek.
5. FM 548 NB/SB. Flagging Operation. Daytime. 9A-3P. Drainage work and bridge activities at Pond Branch.
6. 30 Eastbound Frontage Road Left Lane closure from SH 205 to Townsend Dr. Daytime. 9A-3P. Soil Nail Activities.
7. 30 Westbound Frontage Road. Flagging Operation. From Fate Main PL to FM 551. Daytime. 9A-3P. Embankment activities and placing Riprap/Curb at the on-ramp before FM 551 Westbound Frontage Road.
Monday, May 12th thru Thursday, May 15th:
1. 30 Eastbound, the Right Lane will be closed from SH 205 to John King. Overnight. 9P-5A. Install CSB.
Tuesday, May 13th thru Saturday, May 17th:
1. 30 Westbound, Alternating Lanes closed from Erby Campbell to FM 551. Overnight. 9P-5A. Relocate CSB/Temp Pave Markings installations
o Ramp Closures (as needed): Exit 75 to Westbound Frontage Road; Exit 73 to FM 551.
2. 30 Westbound Frontage Road, the Left Lane will be closed from Townsend Dr to SH 205. Daytime 9A-3P. Drainage Activities.
Contractor crews will work with EMS, fire, and police to allow access through the closure should emergencies occur.