Sunday, July 20th thru Saturday, July 26th:
1. 30 Eastbound Left Lane from FM 548 to FM 2642. Overnight. 9P-5A. Bridge activities at FM 35 and Sabine Creek.
2. 30 Westbound Left Lane from FM 2642 to FM 548. Overnight. 9P-5A. Bridge activities at FM 35 and Sabine Creek.
3. 30 Westbound Left Lane from Fate Main PL to FM 3549. Overnight. 9P-5A. Removals and Placing Hot Mix.
Monday, July 21st thru Saturday, July 26th:
1. John King East to West U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
2. John King West to East U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
3. FM 548 NB/SB. Flagging Operation. Daytime. 9A-3P. Drainage work and bridge activities at Pond Branch.
4. 30 Eastbound Frontage Road Left Lane from SH 205 to Townsend Drive. Daytime. 9A-3P. Embankment and removals.
5. 30 Westbound Frontage Road Left Lane from Townsend Drive to SH 205. Daytime. 9A-3P. Embankment and removals.
6. FM 3549. East to West U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
7. FM 3549. West to East U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
8. 30 Eastbound Left Lane at FM 3549. Overnight. 9P-5A. Embankment and Removals.
Contractor crews will work with emergency medical services, fire, and police to keep access open during the closure for emergencies.