Saturday, August 16th:
1. I-30 Eastbound Frontage Road from SH 205 to John King. Flagging Operation. Daytime. 9A-3P. Install LPCB.
Sunday, August 17th thru Saturday, August 23rd:
1. I-30 Eastbound Left Lane. FM 2642 to FM 548. Overnight. 9P-5A. Bridge and earthwork activities at Sabine Creek and FM 35.
2. I-30 Westbound Left Lane from FM 2642 to FM 548. Overnight. 9P-5A. Bridge and earthwork activities at Sabine Creek and FM 35.
3. I-30 Westbound Left Lane from Fate Main PL to FM 3549. Overnight. 9P-5A. Placing Hot Mix & Pavement activities.
4. I-30 Eastbound Left Lane at FM 3549. Overnight. 9P-5A. Embankment and removals.
Monday, August 18th thru Saturday, August 23rd:
1. John King East to West U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
2. John King West to East U-turn closure. Daytime. 9A-3P. Bridge activities at John King.
3. FM 548 NB/SB. Flagging Operation. Daytime. 9A-3P. Drainage work and bridge activities at Pond Branch.
4. FM 3549. East to West U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
5. FM 3549. West to East U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
6. I-30 Westbound Frontage Road Left Lane from Erby Campbell to FM 548. Daytime. 9A-3P. Embankment and removals.
Contractor crews will work alongside EMS, fire, and police to guarantee access through the closure for any emergency situations that may arise.