Sunday, September 28th thru Saturday, October 4th:
1. I-30 Eastbound Left Lane from FM 548 to FM 2642. Overnight. 9P-5A. Bridge and earthwork activities at Sabine Creek and FM 35.
2. I-30 Westbound Left Lane from FM 2642 to FM 548. Overnight. 9P-5A. Bridge and earthwork activities at Sabine Creek and FM 35.
3. I-30 Eastbound Left Lane at FM 3549. Overnight. 9P-5A. Embankment, Removals, Place Cement Treated Base.
Monday, September 29th thru Saturday, October 4th:
1. FM 548 NB/SB. Flagging Operation. Daytime. 9A-3P. Embankment, Removals, and bridge activities at Pond Branch.
2. FM 3549. East to West U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
3. FM 3549. West to East U-turn closure. Daytime. 9A-3P. Bridge activities at FM 3549.
4. I-30 Westbound Frontage Road. Flagging Operation. FM 35 to Erby Campbell. Daytime. 9A-3P. Install LPCB and Place Hot Mix.
Contractor crews will coordinate with EMS, fire, and police to ensure that access is maintained through the closure for any emergency situations that may arise.